SUMMARY AND CONCLUSIONS
Aims and Objectives
The aims of the Review are to:
- Maintain and improve educational standards
- Maximise the use of existing resources (land, buildings and
funding)
- Increase access to high quality facilities for children, staff
and the community
- Make the choice of a local school the natural and easy choice
for parents
This area is characterised by the absence of all-through primary
schools and the almost total absence of denominational provision.
Most schools are located on generous sites and in generous
buildings although one school is particularly badly served in terms
of the site area available.
The vast majority of children attending these eight schools live
within the immediate and surrounding area. This has potential
benefits in terms of promoting and enhancing community
cohesion.
Unit costs per head vary quite widely within the range £2255 -
£3212.
On average just over 25% of available places each year since
1997 have not been taken up. However, there has been a considerable
reduction in the number of places offered since 1997. Almost 100
fewer places were offered in 2003 than in 1997. A further reduction
for 2004, following the abolition of Standard Number, is
planned.
In September 2003 there were 82 unfilled Infant and 179 unfilled
Junior places in the 8 schools. The proportion of places
unfilled at September 2003 is almost 15% and forecasts indicate
that this will increase to approximately 20% by September
2007. Six of the schools have more than 30 unfilled
places.
There are currently 1682 places in these schools against a
number on roll of 1441 and a further fall to around 1350 is
predicted in the latter part of this decade. The forecast decline
in pupil numbers is principally based on the decline in population
in the wards in which these schools are located. At April 2003 the
number of children aged under 1 is 84% of the number of children
aged 5.
Allowing a 5% error rate and a further 5% for ‘windfall’ housing
developments and any impact of other changes to schools elsewhere
in Bath it is reasonable to assume we need 1500 places and thus
just over 180 places need to be removed.
Closure of a single infant school is not considered feasible
since there are only 82 unfilled Infant places. Closure of a
Junior school is not considered feasible since all four Junior
schools have approximately 200 pupils. If one school were to
be closed the three remaining Junior schools would have less than
150 spare places to accommodate the approximately 200 pupils
needing places due to the closure.
In addition, closing either a Junior or Infant school would
create problems of transfer and continuity between the Infant and
Junior phases.
Each school has been considered in isolation but, ‘paired and
shared’ schools, where infant and junior schools have a natural
relationship with each other both in terms of pupil transfer and in
terms of physical location, have also been considered together when
seeking solutions.
Moorlands Infant School has few unfilled
places. Levels of recruitment against Standard Number have improved
over recent years although some of this improvement can be
attributed to a reduction in Standard Number as a consequence of
the infant class size legislation. It is located on a very generous
site in buildings which are also very generous. There is a
relatively high level of outstanding repairs and maintenance which
reflects the age and type of construction of the building. For some
years a private nursery known as Happy Days operated from the
Infant school site and this provision has now been taken over by
First Steps Nursery working in association with Sure Start.
Moorlands Junior School has approximately 13%
unfilled places. Levels of recruitment have fallen in recent years.
It is located in buildings approximately 70 metres from the Infant
school. Site and building areas available to the school are fairly
generous and in excess of DfES guidelines. This school also has a
relatively high outstanding maintenance liability.
It would be possible to amalgamate these two schools without
major capital investment. Such an amalgamation would result
in some savings, primarily on management costs and improved
continuity and progression from Key Stage 1 to Key Stage 2.
Amalgamation could also release a small part of the joint site for
disposal, which could generate funds to improve the
buildings. However, the two buildings are separate and an
amalgamation in the existing buildings could create difficulties in
effective management of the school.
Consideration should be given to amalgamation of these
two schools on the existing site at a future date when sufficient
funding is available to provide new buildings.
Southdown Infant School currently has almost
20% of its places unfilled and this reflects the pattern over the
last few years. Levels of recruitment moved up to 90% in the early
part of this decade but in 2003 declined to 72%. The site and
buildings are well in excess of that recommended by DfES.
Outstanding maintenance is relatively high reflecting the age of
the building. The school operates a nursery class, and some of the
elements of an “extended school” with a breakfast club.
Southdown Junior School has almost a quarter of
its places unfilled although the position has improved since the
end of the 1990s. The site is undersized but the buildings are well
over double the size recommended by DfES. Maintenance liabilities
are fairly high.
These schools represent an opportunity for amalgamation. The
combined school roll at September 2003 is 330 and is therefore
within the maximum ideal size for a primary school. Levels of
recruitment at the Infant school have fallen into the mid-40s and
thus a 315 place school seems appropriate. As these schools are
regarded as ‘strategic schools in areas of educational deprivation’
serious consideration should be given to creating a new primary
school in new buildings on the existing sites. The joint sites
represent an opportunity to develop an extended school and there
may still be an opportunity to dispose of some surplus site area in
the hope of generating funds for such a scheme. Colleagues involved
in the Sure Start Programme have expressed an interest in locating
services at Southdown and this would be of major benefit in
developing a new extended school.
Consideration should be given to the closure of both
these schools and the creation of a new 315 place extended primary
school in new buildings on the existing sites. A bid for funding
for the scheme should be submitted to the DfES under the Targeted
Capital Fund (should this continue in its present form) and be
considered as a priority for future capital allocations from the
Council and DfES. Every effort should be made to ensure that Sure
Start are able to move onto the site.
St Michael’s CE VC Junior School, Twerton is
the only denominational provision in this area. It has almost a
quarter of its places unfilled. Levels of recruitment varied widely
in the late 90s and 80% was reached in 2002 but this fell back to
just under 70% in 2003. The site is undersized although the
buildings are well in excess of the recommended size. First Steps
Nursery have opened an Early Excellence Centre on the school site.
The condition of the school building is fairly poor with a high
level of maintenance liabilities.
Twerton Infant School has 18% of its places
unfilled. Levels of recruitment have generally been below 50 per
year. The site is large and the buildings are slightly in excess of
the recommended size.
The two Twerton schools cannot realistically be amalgamated at
present. The sites are some distance from each other and it is
undesirable to create split-site schools. The relocation of the
infants to the Junior site or vice versa cannot be achieved without
significant capital expenditure. Despite the fact that the Junior
site is undersized it seems rational to consider, in the medium
term, a scheme to amalgamate on the Junior site. It should be noted
that, as the Junior school is the only denominational provision in
the area, discussions with the Diocese of Bath & Wells would be
needed to clarify whether any new school would continue as
denominational provision.
A study should be undertaken assessing the potential for
an amalgamated school on the Junior site. This study to include an
assessment of the potential value of the Infant school site and the
potential for alternative development on the site in order to
generate part of the capital funding required for the construction
of a new school. The outcome of this study to be reported to the
Executive by July 31st 2005. The initial views of the Diocese of
Bath & Wells should also be sought. In the immediate future, an
assessment of the means by which surplus places can be removed from
the Junior school should be carried out and the necessary action
taken.
Oldfield Park Infant School is currently short
of places although ongoing building works will eliminate this
shortfall. Levels of recruitment are improving and the school was
filled at Reception age in September 20003. The site and buildings
are a little undersized but this appears to cause no significant
difficulties. Outstanding maintenance costs are fairly high but
this is unsurprising given the age of the building. The school
offers some of the elements of the ‘extended school’ with
after-school provision and a breakfast club planned to begin in
September 2004.
Oldfield Park Junior School has almost 15% of
its places unfilled. Levels of recruitment appear low although this
relates to the existence of an unrealistic Standard Number for the
period in question. This admission number has been reduced for
September 2004 and therefore levels of recruitment are likely to
improve. Outstanding maintenance costs are very low. The principal
problem facing this school is the fact that the site is extremely
undersized and it has no access to a playing field. This latter
problem is a breach of legislation. A reservation exists in the
emerging Local Plan in order to allow the creation of a playing
field at some point in the future but the likelihood of the
Council, in the foreseeable future, being able to acquire the
necessary land is slim. The relocation of the school represents the
only realistic chance of resolving the problems with the site and
facilities. A review of the school and its partner Infant school
was undertaken a few years ago in order to ascertain whether
amalgamation could be achieved on the Junior site. The Education
Committee concluded that the costs of such a scheme were not
supportable. In view of the desirability of creating all-through
primary schools this issue requires re-examination.
Consideration should be given to amalgamating the
Oldfield Park schools on a new site. A site needs to be identified
and, in the next eighteen months, a search for such a site should
be undertaken. An assessment of the value to be achieved through
disposal of the existing sites should also be undertaken in order
to assess the opportunities for funding, in part, the provision of
a new school.